| Project Name: Lewis Street Construction |
| Owner: City of Rockford, Michigan |
| Date Completed: 2008 Construction Season |
| Pre-Bid Estimate:
$860,000.00 |
| Contact: Michael Young, City Manager |
| |
 |
| The project which was locally funded, included the design for the reconstruction of approximately 2100 feet of roadway. It also included the replacement of 1925 feet of sanitary sewer, 2275 feet pf watermain and the addition of a storm sewer system. |
 |
| Paradigm Design, Inc. provided surveying, horizontal and vertical alignment, pavement section design, sanitary sewer and watermain design and permitting, storm sewer design, construction cost estimates and construction drawings and specificitions.
|
 |
To be determined.
|
 |
| To be determined. |
|